The Study and Survey process requires a full update of the school district’s area in the ICOS database, as well as a report in PDF format uploaded into the Study and Survey section of ICOS. This information provides a complete overview of the district’s facilities, current conditions, and planned capital needs.
These should be done by the school district and/or consultant, and includes various items such as site plans, building area analyses, condition assessment summaries, financial analysis of the district, capital long-term plan and list of potential projects. Together, these items provide the information needed to support the Study and Survey process and document the district’s facility needs.
Consult your Regional Coordinator for guidance on the Study and Survey report and in updating ICOS.
Content of a Study and Survey Report
| Chapters | Contents |
|---|---|
| Cover and Preliminaries |
|
|
Chapter 1: Inventory and Area Analysis of Existing Facilities |
|
| Chapter 2: Long Range Plan |
Option A: This option is for districts that regularly prepare 6-year Capital Facilities Plans to meet Growth Management Act and/or Impact Fees requirements. Option B: This option is for districts that do not regularly prepare 6-year Capital Facilities Plans. |
| Chapter 2: Supplements |
The supplements to Chapter 2 consist of OSPI input and input from the District / Consultant OSPI Input: Report 1049 & the Diversity Report District Input Tab 1: Form 1066 regarding students with developmental disabilities Tab 2: Financial and Bond/Levy Status Tab 3: Proposed New Facilities, Additions, Modernizations or Replacements Tab 4: School Housing Emergency, if applicable For each Modernization or Replacement project upload a Cost-Benefit Analysis and rationale as to why the project was selected. Upload a timeline for all projects in Tab 3. See the Study and Survey Workbook for details on what to upload to ICOS. |
| Chapter 3: Optional Items/Chapters |
Non-required documents uploaded at the District’s discretion, such as:
|