701: (PDB) D-Forms Overview

Contact Information

School Facilities & Organization Regional Coordinators

Veronica Perez

Eastern Regional Coordinator
360-725-6111

Heidi Burkart

Northwest Regional Coordinator
360-725-4965

Phil Partington

Southwest Regional Coordinator
360-725-4971

Early in the planning stage, a school district should work with its OSPI Regional Coordinator (See "Participants, Roles and Partnerships" in the Introduction section of this manual) to determine if it has School Construction Assistance Program (SCAP) eligibility that can be used toward one or multiple projects (See Chapter 3: School Construction Assistance Program Eligibility).

The application process of requesting SCAP funding assistance for a project begins with the submission of form D-3, OSPI approval of that form and then the issuance of form D-4. However, before a district can submit form D-3, it must have a completed and approved Study and Survey report, which verifies square footages of district facilities, updates the district long-term capital plan, looks at its bond-to-debt capacity, among other things. (See Chapter 11: Advanced Planning—The Study and Survey).

Once a project has begun the application process by being issued a D-4, there are several steps the district must reach during the design phase before it will be allowed to sign construction contracts (or, in the case of GC/CM and PDB projects, execute the final GMP). This chapter details each step of the D-Form, how those steps can vary depending on the project delivery method, key deadlines for districts to pay attention to, lessons learned and more.

SCAP is a unique grant program in that the funds are not yet available to be issued to the district at the point when it begins this application process. The purpose of the D-form process is to help OSPI track a project's status, and viability as it moved toward eligibility for state funding assistance. 

In its current form, SCAP is mainly designed for a Design-Bid-Build (DBB) project delivery method but can also accommodate General Contractor/Construction Manager (GC/CM) and Design-Build (DB) methods. This chapter will outline the process of the D-Forms by the three procurement types it can accommodate (DBB, GC/CM and DB). 

D-Forms Summary Chart (For Progressive Design-Build Projects) 

D-Form Application Highlights Approval (Issued by OSPI) Deadline for Next D-Form Application
D-1: Study and Survey Grant Application
  • Project Planning
  • Certify Facility Inventory
D-2 The district must have an updated and approved Study and Survey within six years of submitting a D-3. OSPI reserves the right to request an update to that Study and Survey within that six-year period.

D-3: Project Application

Occurs when submitted a project for SCAP funding

  • Eligibility Calculation
D-4 A D-5 is due one year (or sooner) after receiving a D-4
D-5: Application for Preliminary Funding Status
  • Environmental Review (SEPA)
  • Site Visit by Regional Coordinator
D-6 A D-7 is due one year (or sooner) after receiving a D-6 or D-6(1)

D-7: Application to Negotiate the Final GMP Amendment

For PDB projects, a D-8 or D-8(1) (see "Front-Funding versus Non-Front-Funding" is not required before issuing early bid packages. Unlike Design-Bid-Build projects, where the D-8/D-8(1) is associated with authorization to proceed with the construction bid, PDB projects may proceed with early bid packages before the D-8/D-8(1) is issued. However, these early bid packages many not include construction on the building itself. 

  • Contracts
  • Cost Estimates
  • Area Analysis
  • Agency Approvals
D-8

A D-9 is due 90 days after receiving a D-8 or D-8(1). If the project is estimated at least 10 percent over budget and the school district can show that, it can request an extension of an extra 90 days. This must be approved by OSPI, however. 

D-9: Application for Authorization to Sign Final GMP Amendment

A D-10 or D-10(1) must be received before the final GMP Amendment can be signed

  • Advertisements
  • Bid Tabulation
  • Bid Form
  • Final Billings
D-10 Projects cannot break ground on building until D-10(1) or D-10. See "001: Terms Used" in the Introduction chapter for more information on "breaking ground."
D-11: Application to Release Retainage
  • Final Payment to General Contractor
D-12  

 Contact your OSPI Regional Coordinator with questions.